All citations for Grace Village Health Care Facility
State inspectors check nursing homes that take Medicare or Medicaid against federal rules, usually about once a year, and also look into complaints. Each rule a home did not meet is a citation.
Last standard health inspection on record
March 24, 2025
Showing 26 to 44 of 44 citations
No harm, with potential for more than minimal harm
Ensure receptacles at patient bed locations and where general anesthesia is administered, are tested after initial installation, replacement or servicing.
The home gave a date the problem would be corrected (June 1, 2023).
No harm, with potential for more than minimal harm
Meet requirements for sections of health care facilities separated by fire resistive construction.
The home gave a date the problem would be corrected (May 18, 2025).
No harm, with potential for more than minimal harm
Meet other general requirements that are deficient.
The home gave a date the problem would be corrected (May 18, 2025).
No harm, with potential for more than minimal harm
Ensure smoke barriers are constructed to a 1 hour fire resistance rating.
The home gave a date the problem would be corrected (May 18, 2025).
No harm, with potential for more than minimal harm
Have properly installed electrical wiring and gas equipment.
The home gave a date the problem would be corrected (May 18, 2025).
No harm, with potential for more than minimal harm
Have exits that are accessible at all times.
The home gave a date the problem would be corrected (July 13, 2024).
No harm, with potential for more than minimal harm
Provide properly protected cooking facilities.
The home gave a date the problem would be corrected (July 13, 2024).
No harm, with potential for more than minimal harm
Construct fire resistant interior walls.
The home gave a date the problem would be corrected (July 13, 2024).
No harm, with potential for more than minimal harm
Inspect, test, and maintain automatic sprinkler systems.
The home gave a date the problem would be corrected (July 13, 2024).
No harm, with potential for more than minimal harm
Have properly installed electrical wiring and gas equipment.
The home gave a date the problem would be corrected (July 13, 2024).
No harm, with potential for more than minimal harm
Have restrictions on the use of highly flammable decorations.
The home gave a date the problem would be corrected (July 13, 2024).
No harm, with potential for more than minimal harm
Ensure proper usage of power strips and extension cords.
The home gave a date the problem would be corrected (July 13, 2024).
No harm, with potential for more than minimal harm
Conform to length requirements for dead end corridors.
The home gave a date the problem would be corrected (June 1, 2023).
No harm, with potential for more than minimal harm
Have properly located and lighted "Exit" signs.
The home gave a date the problem would be corrected (June 1, 2023).
No harm, with potential for more than minimal harm
Ensure that special areas are constructed so that walls can resist fire for one hour or have an approved fire extinguishing system.
The home gave a date the problem would be corrected (June 1, 2023).
No harm, with potential for more than minimal harm
Have properly installed electrical wiring and gas equipment.
The home gave a date the problem would be corrected (June 1, 2023).
No harm, with potential for minimal harm
To conduct inspection, testing and maintenance of fire doors by qualified individuals.
The home gave a date the problem would be corrected (July 13, 2024).
No harm, with potential for minimal harm
Ensure heating and ventilation systems that have been properly installed according to the manufacturer's instructions.
The home gave a date the problem would be corrected (June 1, 2023).
No harm, with potential for minimal harm
Have simulated fire drills held at unexpected times.
The home gave a date the problem would be corrected (June 1, 2023).
Source: CMS Provider Information, Fire Safety Deficiencies, Health Deficiencies, Citation Code Look-up, data as of October 1, 2026. Inspection results describe the home at the time of each inspection.